Skip to content

997,20 kWp Torremaggiore (FG), Apulia

About the solar installation:

>       System size:        997,20 kWp
>       Location:              Torremaggiore (FG), Apulia
>       Completed:          Q2/2011
>       PV installation:   ground mounted, static
>       Covered area:      2.20 ha
>       Solar panels:       5.540x NINGBO ULICA SOLAR UL800 180Wp si mono
>       Inverters:             2x SMA Sunny central SC-500-CP-10
>       Specific yield:     1.404 kWh/kWp
      Annual output:   1.397.766 kWh/year
>       Sponsor:               SOLAR ELECTRIC SRL (SPV and Operator)
>       Advisors:              PENSATO+PARTNERS

Activities: Project development and structuringprocurement, contracting, tender management, executive Engineering, EPC works supervision, project management and coordination, direction of the works, safety and security, grid connection, UTF / GSE License, progress reporting, arrangement of debt finance, after sales and O&M services, Asset management.

>      O&M contractor: PENSATO+PARTNERS
>      Technical and commercial management: PENSATO+PARTNERS